Kozienice modernise their units
The Kozienice Power Plant will modernise the turbine sets on units 3 and 6. Alston Power and Metal Expert consortium will perform the modernisation. Parts of steam turbines will be improved. The modernisation will enable lowering of a unit consumption of heat by 120 kJ/kWh and increase in the electric power by min. 3 MW for each unit. Re-commissioning of the modernised unit no 3 is planned till 23 August 2012. Unit no 6 will undergo modernisation till 6 December 2012. The undertaking will cost almost PLN 30 mln net.
Having in mind the diverse and international nature of Enea SA's shareholding, and also the provisions of the Best Practices of WSE Listed Companies, Enea SA guarantees the availability of its website also in English. In case of any interpretation doubts and discrepancies between the Polish and English versions, the Polish version shall prevail.